- Cairnmore Hill Wind Farm (Re-design) - Erection and Operation of a Wind Farm for a period of 35 years, comprising of 5 Wind Turbines with a maximum blade tip height 138.5m, access tracks, substation, control building, battery energy storage system, and ancillary infrastructure.
- Deadline
- 12/01/2025
- Status
- Under Consideration
- Capacity turbines
- 21.5 MW
- Number of turbines
- 5.0
- Height turbines
- 138.5 m
- Comment
- This is a highly contested application with hundreds of objections and hundreds of letters of support. This latest design has 5 very high turbines and a BESS very close to Thurso. There are no details given about the Battery Energy Storage System (BESS for short). Considering the imminent danger of a BESS the lack of detail is very concerning.
UPDATE: An Environmental Impact Assessment (EIA) and Supplementary Environmental Information (SEI) has been submitted for the highly contested development. Representations can be sent in again.